Podilskiy Energoconsulting

Substation “ Zhmerynka”

LLC “ Podilskiy Energoconsulting” has performed reconstruction project of the substation 110/35/10 kV "Zhmerynka". There were developed design solutions of the replacement of the power transformer T-1 type TDTNH-16000/110 with a new type TDTN  16000/110 and high voltage equipment cell 110 kV and 35 kV T-1 with the replacement of physically worn reinforced concrete portals and support pillars, as well as reconstruction of relay protection of T-1. In addition, according to this project it is done the replacement of the existing 10 kV current transformers T 1. The reconstruction of the substation will increase the reliability of electricity supply to consumers of Vinnytsia region.

Substation “ Zhmerynka”

It was completed the reconstruction project of the substation 110/35/10 "Zhmerynka"