Podilskiy Energoconsulting

It is completed the building of Photovoltaic Power Plant of LLC “Rendgy Trostianets”.

It is completed the building of Photovoltaic Power Plant on the territory of the village council of Hlybochok, Trostianetskyi district, Vinnytsia region. The first starting complex is with the power of 2,25 MW.
Power distribution of the second phase in the PJSC “Vinnytsiaoblenergo” is performed by two CL-10 KV, one of which connects the switchgear-10 KV of the project station to the switchgear-10 KV of accounting unit of the first phase of construction, and the other to 1 section switchgear-10 KV of substation 110/35/10 KV “Hlybochok”.